An important and final stage of the turbine installation has been completed at the first unit of Rooppur Nuclear Power Plant.
Bangladesh's first nuclear power plant continues to progress towards starting up, with the turbine installation completed at ...
The key stage of placing the turbine set on the barring gear has been completed at Rooppur Nuclear Power Plant Unit 1 in ...
Rooppur Nuclear Power Plant (RNPP) authorities have successfully conducted the hydraulic pressure tests in first of their two ...
This is an important step to the physical start-up of the plant, Alexey Deriy, Atomstroyexport vice president for projects, says ...
To ensure the strength of the primary circuit systems and equipment, hydraulic tests with a pressure of 24.5 MPa have been ...
A 50-tonne capacity bridge crane for the second unit of Rooppur Nuclear Power Plant is ready for shipment from the Russian ...
A 50 tons capacity bridge crane for the second unit of Rooppur Nuclear Power Plant is ready for shipment from the Russian ...
Chief Adviser Professor Dr. Muhammad Yunus today said they have been putting importance on timely completion of the Rooppur Nuclear Power Plant con ...
The hydraulic tests to check the primary circuit systems and equipment at the Rooppur nuclear power plant's first unit have ...
Russia could supply a small nuclear power plant for a mission to Mars planned by billionaire entrepreneur and SpaceX CEO Elon ...