News

Lower Colorado River Authority recently put two separate plants at its Lost Pines Power Park under one functional management system. The project has already deployed a layered wireless ...
LCRA plans to build two electric generating units at LCRA’s natural gas-fired peaker Timmerman Power Plant in Caldwell County, with the first unit expected to be online later this year.
Water officials in Texas are urging everyone to remain out of Lake Travis as debris flow and high bacteria levels from the ...
The new unit will be built on the same 51-acre site where construction on the first unit of a new LCRA peaker plant is underway.
A second generating unit will be added to the new peaker power plant under construction in Caldwell County, Texas.
This last legislative session, lawmakers were set to hire LCRA to build a $10 billion fleet of gas plants to use as backup power during times of grid strain – that bill ultimately failed, but it ...
In its press release, the LCRA insists that Fayette "keeps emissions well below levels allowed by law" and is one of the state's "cleanest coal-burning power plants." ...
The Lower Colorado River Authority is planning to build a new peaker power plant in Central Texas to support the Texas electric grid when needed.
MAXWELL, Texas (KXAN) —On Friday, the Lower Colorado River Authority announced it was building a peaker power plant in Caldwell County set to be operational by 2025. According to a release from ...
LCRA adds scrubbers to clean sulfur dioxide from plant emissions Environmentalists push for plant's closure, but Austin opts for reliable energy.
Due to ongoing drought conditions, the Lower Colorado River Authority said it would consider moving to Stage 2 of its drought response March 1.
A natural gas power plant next to the Guadalupe River in Victoria. The Texas Senate's plan to spur construction of more gas-fired power plants across the state for emergencies will cost about $7 ...